Sustainable Infrastructure Assistance Program - Supporting Sustainable and Universal Electricity Access
Project Details
Country: Vietnam
Detailed Narrative Description of the Project:
Using
various tools for system assessment as desk reviews, meetings, consultations,
and field visits, the
international specialist, assisted by a national specialist, will:
(i)
assess the current Government of Indonesia (GOI)'s resettlement and indigenous
people (social) safeguards system for managing social impacts and risks;
(ii)
prepare Program Safeguards System Assessment (PSSA); and
(iii) give social safeguards related inputs to PAPs
for RBL program. The assessment analysis will build on past and existing
studies carried out by ADB for country safeguards system (CSS) for PLN (TA 8548)
and assessment on safeguards from previous energy RBL programs. The PSSA
exercise will include; (a) diagnostic assessment of applicable and relevant
laws, regulations, rules, and procedures for managing and mitigating the social
safeguards impacts of RBL program;(b) an assessment of PLN's implementation
practice, capacity and commitment to plan, implement, monitor and report on the
safeguards measures for RBL program;(c) the RBL programs' inconsistency with
the applicable ADB Safeguard Policy Statement (SPS) 2009 principles (as
relevance), the significance of these gaps, and PLN's commitment to address
critical gaps; and; (d) social safeguards related program actions to be
included in the overall PAPs for RBL program to address the identified
weaknesses. The PAPs will follow the SPS objectives and principles, but the policy
delivery process and operational procedures will refer to the country system.
Detailed Description of Actual Services Provided by SAMES:
The specialists shall
ensure that all works, and outputs are fully compliant with relevant ADB, GOI,
and PLN policies and guidelines. The specialists' work shall include, but not
limited to, the following tasks:
(i) Review equivalence
and acceptability assessments reports for PLN's use of country safeguards system
(CSS) carried out by ADB in collaboration with PLN and BAPPENAS and existing
PSSA reports for Indonesia: Sustainable Energy Access in Eastern Indonesia-Electricity
Grid Development Program
(ii) Propose an initial categorization for RBL
program's potential social impacts and draft ADB categorization forms for
involuntary resettlement and indigenous peoples. The categorization will be determined
by the most sensitive activity in program, not by the aggregation of impacts of
all program activities. The level of comprehensiveness and details of
assessments and measures will be commensurate with the results of this
categorization.
(iii) Prepare inception
report that includes:
-scope of
PSSA work
-approach,
methods, and timeframe of assessment,
-plan for
consultation (based on the stakeholder mapping and program scope) and
disclosure of PSSA reports and PAPs on ADB and Executing Agency.
(iv) Review documents
on applicable and relevant government laws, regulations, rules, and procedures
for managing and mitigating the social safeguards impacts of the RBL program.
(v) Assess key
inconsistencies/gaps between the Indonesian law and regulations and PLN's
Decrees with ADB SPS principles and whether the written system (law,
regulations, procedure) addresses safeguards principles set forth in ADB SPS.
Identify what incremental improvements are needed.
(vi) Assess the
implementation of written system and capacity of the EA, implementing agencies and other key agencies in handling social safeguards. Identify what
incremental improvements are needed. Capitalize the gap analysis and capacity
assessment in handling social safeguards under equivalence and acceptability
assessment for PLN, PSSA reports and relevant ADB financed projects framework
for energy with PLN for the assessment and action plans.
(vii) Select the most
social -sensitive programs (including geographic area, potential impacts on resettlement
and indigenous peoples, and communities acceptance) to be financed under the
RBL program (completed, ongoing, or planned activities), and conduct field
visits to assess compliance with ADB/GOI- PLN social safeguards policies.
(viii) In collaboration
with PLN, organize consultation meetings with the communities and local leaders
including customary leaders and village offices, relevant local government
agencies (Regional Land Office (KATR/BPN), Provincial and District Government
handling social welfare and indigenous people), civil society organization
(CSO), PLN regional offices (PLN Wilayahs and the units below), and other
stakeholders in the at regional level where selected program are located.
(ix) Assess the
adequacy of how EA/IA has implemented its own projects as well as ADB/IFI
projects on a macro level. Assess the commitments of EA/IA at national and
regional level in addressing the gaps.
(x) Based on the legal
review and capacity assessment, prepare social safeguards related actions to be
included in the overall PAPs to address the identified gaps/weaknesses in
framework and capacity both for involuntary resettlement and indigenous
peoples. The actions that may include
-specific
mitigation measures to address particular impacts;
-institutional
arrangement, cost estimates, budget, and time frame for implementing the
actions; and
-measures
for information disclosure, consultation, and grievance redress during
implementation
-The action will focus
for the key priority actions and be selective in its coverage. The type and
content of agreed actions are determined by reference to the PSSAs findings and
should be commensurate with the significance of social safeguards issues
associated with the RBL programs. The actions may include measures for
monitoring social safeguards systems performance.
(xi) Prepare draft PSSA
reports for RBL program containing assessment and social safeguards related
program actions and be made available for the key stakeholders prior to the
consultations. Use outline of ADB PSSA for the report preparation.
(xii) In collaboration
with the PLN HQ and PLN Wilayah and other consultants under the RBL programs,
organize consultations with key stakeholders on the draft PSSAs and PAPs and
get participants view and suggestions/recommendations
for the draft. The stakeholders include representatives affected persons and
community leaders, Ministry of Energy and Mineral resources (MEMR), Land Office
(KATR/BPN), local government agencies, PLN, CSOs, and other relevant agencies
at regional level where program are located. Give [social safeguards related
inputs to minutes of consultations and recommendations.
(xiii) Finalize the
PSSA reports in collaboration with social safeguards specialists and give
social safeguards related inputs to PAPs. Secure the agreement from ADB and
EAs.
(xiv) Undertake additional tasks to be assigned by the
Team Leader or Social Safeguards Specialist, ADB